Issues Emerge in Oracle's AI Data Center Expansion in Major New Mexico Project

Issues Emerge in Oracle's AI Data Center Expansion in Major New Mexico Project
Summary
Oracle's 'Project Jupiter' faces power supply and permitting challenges in New Mexico.
The company signed inflexible lease terms obligating full rent despite project setbacks.
Recent partner departure and permitting issues delay the project's completion to late 2028.

Share

Bookmark

Newsletter

In August, a group of protesters gathered in Santa Fe, New Mexico, to voice their opposition to Oracle’s ambitious ‘Project Jupiter’ data center initiative. The tech giant embarked on this project last year, aiming to lease a significant AI data center campus located in Doña Ana County. This endeavor is part of a broader strategy to bolster computing capabilities for OpenAI through a series of aggressive deals.

Oracle's commitment to the New Mexico facility is substantial, featuring lease terms that leave little room for flexibility. Designated as "hell-or-high-water," the agreement mandates that Oracle continue to pay rent regardless of its ability to secure necessary power for the operation of the data centers. This situation has raised concerns, as Project Jupiter now faces delays and difficulties concerning power supply and the requisite permits.

In response to initial local pushback against its plans to utilize gas turbines and diesel generators for power, Oracle revised its energy strategy. However, the company still has not received the vital air permits from state authorities. It is also encountering complications regarding a segment of a proposed 17-mile natural gas pipeline, which has faced opposition due to its planned route crossing state land, leading to two rejections thus far.

Further complicating matters, Oracle has recently severed ties with one of its crucial partners responsible for land and power for the development, according to insider sources. This week, Oracle notified Stack Infrastructure—the developer managing the site, which is backed by Blue Owl Capital funds—of a force majeure, indicating it would delay the timeline for full rent payments. The lease allows Oracle to postpone its payments for as long as three years, with the first phase of Project Jupiter initially projected to finish by the third quarter of 2028.